Ridge Street Bridge Work On Schedule
Construction on the Ridge Street bridge in Rye Brook is on schedule, according to an update from the Village of Rye Brook sent June 28.
The work began on May 6 and the bridge will remain closed until Aug. 16-26, 2012. All construction is expected to be completed by Sept. 4, 2013.
Find out what's happening in Ryewith free, real-time updates from Patch.
Current Status as per NYSDOT (updated 06/27/13):
Demolition of existing bridge deck and approaches continues
Find out what's happening in Ryewith free, real-time updates from Patch.
Begin Deck preparations
Day and night shifts scheduled (7 AM - 3 PM) (6 PM - 3 AM)
Nighttime lane closures on I-287 are required
One Week Look Ahead (week of July 1):
Continue deck preparation
Installing shear studs and deck pans
---
Has the construction affected your commute? Discover something new while using an alternate route? Tell us about it in the comments.