Community Corner

Ridge Street Bridge Work On Schedule

Construction on the Ridge Street bridge in Rye Brook is on schedule, according to an update from the Village of Rye Brook sent June 28.

The work began on May 6 and the bridge will remain closed until Aug. 16-26, 2012. All construction is expected to be completed by Sept. 4, 2013.  

Find out what's happening in Ryewith free, real-time updates from Patch.

Current Status as per NYSDOT (updated  06/27/13):

Demolition of existing bridge deck and approaches continues

Find out what's happening in Ryewith free, real-time updates from Patch.

Begin Deck preparations

Day and night shifts scheduled (7 AM - 3 PM)  (6 PM - 3 AM)

Nighttime lane closures on I-287 are required

One Week Look Ahead (week of July 1):

Continue  deck preparation

Installing shear studs and deck pans

---

Has the construction affected your commute? Discover something new while using an alternate route? Tell us about it in the comments. 


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here