When students returned to school on Monday, September 9, the already new-and-improved Rye Middle School/High School revealed a great deal of facilities progress! While the new science wing is under construction, a number of other projects were finished over the summer. The District will provide further updates over the next several months, but current highlights are as follows: 

  • Renovation of select interior classrooms has been completed and the rooms are ready for use!
  • The locker room reconstruction continues as planned. The wrestling room and storage room near the gym will be used as temporary changing rooms for the first few weeks of school.
  • Foundation walls are being installed at the new science wing construction site. The work is moving along on schedule for a September 2014 completion!
  • All three temporary faculty parking areas have been completed with striping and signage. They have been in full use as staff members returned this week.
For more updates and to view photos, visit www.ryeschools.org and click the "Construction Update" icon on the homepage. 